8. 16"-24" Head Platform Assembly

PNEG-1807 16"-24" Bucket Elevator Platform and Ladder “X” Series

49

Install Deck C and Toe Board

1. Locate pre-assembled Deck C, consisting of two (2) planks and connecting tabs.

2. Slide side toe board into place on the drive side of the lower head.

3. Orient the side toe board so that the hole labeled A1 is at the up-leg end and A3 is at the discharge

end of the lower head.

4. Using a punch as needed for alignment, connect Deck C to side toe board using 3/8" x 1" carriage

bolts (S-3585) with flange nuts (S-10028) and torque to standard specifications.

(See Figure 8E.)

a. Deck hole C1 to toe board hole A3.

b. Deck hole C2 to toe board hole A4.

c. Deck hole C3 to toe board hole A1.

NOTE: Due to snug fit, slide side toe board in place before securing Deck C or any subsequent decking.

Figure 8E 24" Deck C Toe Board