Time controlled press (method 3), Enforce – FEC DSP1500 (SAN3) User Manual
Page 92

PAGE 6-30
enFORCE
Operation Manual
♦
Time Controlled Press (Method 3)
This Load Control press method allows a pressing operation to be performed based off
of a given time [42: 2
ND
Time].
Upon start of cycle, the press will operate until it achieves [13: Standard Load]. During
the press cycle, after achieving [18: Crossover Load], the press rate will be current
controlled to achieve [13: Standard Load] in proportion to the time specified in
[42: 2
ND
Time] (Example: if [42: 2
ND
Time] is set to 10 seconds, it will take 10 seconds
to go from [18: Crossover Load] to [13: Standard Load])
. During the press cycle,
checks are performed for “1
ST
Judgment Zone”, 1
ST
Rate, 2
ND
Rate, Load, Distance
and 1
ST
Time. If any of these values are compromised, the press will stop and return as
programmed.
(See corresponding sections for Time, Rate, 1
ST
Zone and Speed explanations.)
This press can be done with an ‘F’ type tool but make sure not to overload.
In this special setup, [42: 2
ND
Time] is a “control” function and is not used for
judgment.
If “1
ST
Judgment Zone” is not used, set [15: 1
ST
Load] to [10: CAL Load] and
[23: 1
ST
Distance] to a minimum of [21: High Distance].
Review Speed Section explanations and cautions when setting [15: 1
ST
Load],
[14: Speed Change Load], [24: Crossover Distance] and [20: Freerun
Distance].
If 1
ST
Rate is not used, set judgment windows wide open; low value of 0 and
maximum high value. Also, if 1
ST
H/L Check is not being used, set [17: Threshold
Load] to [10: CAL Load].
Chapter 6: System Operation
Load
Distance
[12] High Load
[13] Standard Load
[15] 1
ST
Load
[14] Speed Change Load
[17] Threshold Load
[20]
Low
Distance
[21]
High
Distance
[41]
1
ST
Time (Supervision)
[42]
2
ND
Time (Control)
1
ST
Rate
[23]
1
ST
Distance
1ST Judgment Zone
Final Judgment Zone
[18] Crossover Load
[11] Low Load
2
ND
Rate