PAGE 6-27
enFORCE
Operation Manual
♦
Distance Control (Method 1)
Upon start of cycle, the press will operate until it achieves [22: Standard Distance].
During the press cycle, checks are performed for “1
ST
Judgment Zone”, 1
ST
Rate, 2
ND
Rate, Load, Distance, 1
ST
Time and 2
ND
Time. If any of these values are compromised,
the press will stop and return as programmed.
(See corresponding sections for Time, Rate, 1
ST
Zone and Speed explanations.)
If “1
ST
Judgment Zone” is not used, set [15: 1
ST
Load] to [10: CAL Load] and
[23: 1
ST
Distance] to a minimum of [21: High Distance].
Review Speed Section explanations and cautions when setting [15: 1
ST
Load],
[14: Speed Change Load], [24: Crossover Distance] and [20: Freerun
Distance].
If 1
ST
Rate or 2
ND
Rate are not used, set judgment windows wide open; low value
of 0 and maximum high value. Also, if 1
ST
H/L Check is not being used, set
[17: Threshold Load] to [10: CAL Load].
Load
Distance
[12]
High
Load Limit
[16] Snug Load
[11] Low Load Limit
[15] 1
ST
Load
[14] Speed Change Load
[17] Threshold Load
[20]
Low
Distance
[21]
High
Distance
2
ND
Rate
[41]
1
ST
Time
[42]
2
ND
Time
1
ST
Rate
[23]
1
ST
Distance
1ST Judgment Zone
Final Judgment Zone
Chapter 6: System Operation
[22]
Standard
Distance
[24]
Crossover
Distance