2.1.4 Mounting the Inverter
The inverter base can reach a temperature up to 90°C (194°F), and it is recommended that it should

be mounted on a noncombustible surface*. This surface and the mounting hardware must also be

capable of supporting at least twice the weight of the inverter. To meet regulatory requirements,

the MS-AE Series must be mounted in one of the following positions; as shown in fi gure 2-2:

above or under a horizontal surface (shelf or table),
or on a vertical surface (wall) with the DC terminals to the right.

CAUTION: If the inverter is mounted in a way that the DC terminal ventilation openings

are oriented on the bottom, the ME-CB enclosure must be used. This enclosure prevents

burning material from falling out the bottom and also allows suffi cient ventilation to prevent

the inverter from overheating under normal operating conditions.

After determining the mounting position, refer to the physical dimensions as shown in fi gure 2-3

or use the base of the inverter as a template to mark your mounting screw locations. After mark-

ing the mounting screw locations, mount the unit with appropriate mounting hardware.

* Noncombustible surface - A surface made of material that will not ignite, burn, support combustion, or

release fl ammable vapors when subjected to fi re or heat as per the ASTM E136 standard. For the most

part, these are materials that are largely comprised of inorganic materials such as stone, steel, iron, brick,

tile concrete, slate and glass. Common building materials such as gypsum board as well as any paint, wall

coverings, and certainly wood will not pass.


Figure 2-2, Approved Mounting Positions

S helf or Table M ounted

(right -s ide up )

S helf or Table M ounted

(up -s ide dow n )

3 0

30

30

W all M ounted

(D C term inals to the right)

W all M ounted (D C term inals on the bottom *)

* W hen the inv erter is m ounted in this pos ition ,

the M E -C B c onduit box m us t be ins talled .