Procedure:
1. Make sure that no terminal of the PV module is grounded.
2. Use Sunny Portal or Sunny Explorer to determine which of the connected inverters has a
3.
Risk of electric shock due to high voltages
• Disconnect the affected inverter from all voltage sources (see Section 9, page 48).
4. Measure voltages with a suitable measuring device.
• Measure the voltages between the positive terminal and the ground potential.
• Measure the voltages between the negative terminal and the ground potential.
• Measure the voltages between the positive and negative terminals.
If the following results are present at the same time, there is a ground fault in the PV
system:
– All measured voltages are stable.
– The sum of the two voltages to ground potential is approximately equal to the
voltage between the positive and negative terminals.
5. In case of a ground fault, solve the problem and recommission the inverter (see Section 12,
6. If there is no ground fault and the error persists, contact the SMA Service Line.