beautypg.com

1 securing cable to the floor, Securing cable to the floor, Figure 3.1 – RLE LD5100 User Manual

Page 26: Water leak detection cable (sc)

background image

www.rletech.com

26

970.484.6510

3

Installation

Once the leader cable is plugged into the terminal block, it is ready to be connected to the SC

cable. To do this, unscrew the EOL terminator from the end of the leader cable. Attach the first

length of the SC cable to the leader cable. Route the SC cable according to a cable layout

diagram, if provided. Lay the cable according to the cable installation guidelines on pages 9-

10. Secure the EOL terminator on the unoccupied end of the last section of SC cable.

Figure 3.1 Water Leak Detection Cable (SC)

3.2.1 Securing Cable to the Floor

Secure the SC cable to the floor with either J-clips (Part #JC) or one of the other approved

methods shown in Figure 3.2. Available from RLE and designed specifically for use with the

SC cable, J-clips are the manufacturer's recommended installation method and can be installed

as follows:



Place one J-clip every 3 feet (.914m) along the length of the SC cable and one at each turn

of the cable.



If the cable is installed over an obstruction, clip the cable on both sides, as close to the

obstruction as possible.

Do not install the cable directly in front of an air conditioner. Allow a minimum of 6

feet (1.83m) between the unit and the cable. If the cable is too close to the air

conditioning unit's air stream, the moisture from the humidifier may cause false

leak readings. If the cable must be installed in front of an air conditioning unit,

place the J-clips 3 feet (0.914m) apart.

Note It is important to finish the end of the SeaHawk Water Leak Detection Cable (SC) with the end

terminator (EOL). If the EOL terminator is not present, a cable fault will register. Note any

variances between the cable layout diagram and the actual cable installation.

W

ARNING