PB DPV1 / PA Field Unit Installation and Maintenance FCD LMENIM2336-03 – 12/12

flowserve.com

Table 2.7 – Recommended Lengths of PROFIBUS PA Spurs (Stubs)

Number of Spur

Cables

Length of Spur Cable

Intrinsically Safe (m)

Length of Spur Cable

Non-Intrinsically Safe (m)

19 to 24

30

30

15 to 18

30

60

13 to 14

30

90

1 to 12

30

120

NOTE: The maximum lengths are estimates and depend on the condition of the actual cable.

There are several topologies for PROFIBUS networks:

• Daisy Chain – A single cable daisy chained in and out of each device. End devices only have one

cable.

• Tree – Cables and electronic devices (such as repeaters or link modules) are used to branch out

from different points.

• Star – Similar to a Tree configuration but the cables all originate from one centralized point that is

comprised of electronic devices (such as repeaters or link modules).

• Combination of the above.

Figure 2.8 – PROFIBUS PA Cable Topologies

PROFIBUS

Interface

Control Highway

Distributed Control

System (Host)

Junction

Box

Tree

Daisy Chain

Bus with spurs

(or drops)

Point-to-point

Schematic topology: Details such
as terminators and power supplies

not shown