Holidays, Holiday day selection, Holiday start / stop times – Auto-Zone Control Systems Auto-Zone Plus Systems Installation & Operation (Version 03A) User Manual
Page 136

Section 3
Auto-Zone Plus
3-50
Programming
Holidays
Holiday Day Selection
Holiday Start /
Stop Times
The screens will step through the fourteen possible holidays
periods, one at a time. Line 2 shows which holiday is currently
being programmed. Since a holiday period can encompass
more than one day, you need to program the day the holiday
starts and the day the holiday ends. If the holiday is only one
day simply put the start and stop to the samr value.
Remember to combine the month and day into a single four
digit value.
EXAMPLE:
704 = July 4th
1225 = December
25th
Zone Manager
Holiday # 1
Start Mon/Day: 0
(EX: 101 = Jan. 1)
Zone Manager
Holiday # 1
Stop Mon/Day: 0
(EX: 704 = Jul. 4)
Zone Manager
Holiday Schedule
Start Event #1: 0
Stop Event #1: 0
The fourteen holiday periods all use the same Start and Stop
time for each event which is entered on this screen. It is entered
in 24-hour military format, the same as a regular week schedule.
Zone Manager
Holiday Schedule
Start Event #2: 0
Stop Event #2: 0