Preparing for installation, Arning, Mportant – EXFO FG-750 User Manual
Page 38
Getting Started with Your Fiber Guardian
24
FG-750
Preparing for Installation
Preparing for Installation
Before installing your unit, you should take the following into
consideration:
The chosen location provides adequate clearance for maintenance
procedures.
The location is an environmentally-controlled area that meets the
minimum operating parameters.
The location is isolated from strong electromagnetic fields produced by
electrical devices.
The power cable and power supply are compatible with your power
service.
The power source is properly grounded and falls within the internal
power supply rating.
The location is in an ESD-safe work area.
W
ARNING
The unit is designed to be installed in a limited access area, for
example, Central Offices, Telecommunication Centers, computer
rooms, wiring closet and similar type locations and in
accordance with local codes.
Only trained personnel can perform the unit installation and
configuration tasks. These people have appropriate technical
training and experience to be aware of the hazards to which a
person can be exposed when performing these installation
tasks.
I
MPORTANT
Use only shielded cables for Ethernet connections to the unit. The
shielded cables must be grounded at both ends.