INSTALLING THE AT30

4

1.5. MOUNTING THE AT30

Chose the mounting method for the unit enclosure from the table below.

ENCLOSURE

ENCLOSURE

MANUAL

SECTION

MOUNTING METHOD

Style-5018

Style-5030/163/198

1.5.1

Floor-Mounting

STANDARD

STANDARD

1.5.2

Wall-Mounting

OPTIONAL

n/a

19in / 483mm

Rack-Mounting

n/a

n/a

1.5.3

23-24in / 584-610mm

Rack-Mounting

OPTIONAL

n/a

1.5.1. Floor-Mounting the AT30 (standard)

To floor mount the AT30, you must consider the following:

1. Overall footprint of enclosure. Refer to the standard outlines drawing listed

in Appendix C, starting on Page 66.

2. The location:

Should be free of drips and splatter. If dripping liquids are a problem,
install a drip shield. See ordering information in Appendix B on page 65.

Should be between 32 and 122 °F / 0 and 50 °C, with relative humidity
between 5 and 95% non-condensing.

Must be free of flammable or explosive materials.

3. Maintain at least 6in / 152mm of free air on top, bottom and both sides of the

enclosure for air cooling.

4. Allow at least 36in / 914mm front clearance for access to the charger for

operation and maintenance.

5. Be conscious of future input and output wiring to the AT30. Note the

standard pre-fab conduit knockouts located on the sides (and sometimes top)
of the enclosure, featured on the standard outline drawings listed in
Appendix C, starting on Page 66.

PROCEDURE (Style-5018)
1. Install four (4) 0.25in / 6.4mm bolts into the floor per mounting dimensions

featured in the outline drawing (

JE5085-00).

2. Using the methods described in Section 1.4, carefully lift the AT30 above

the floor-mounting bolts. Guide the enclosure onto the floor bolt pattern and
lower it into place.

3. Add appropriate mounting hardware (0.25in / 6.4mm), onto the floor-

mounting bolts and tighten securely.