7 electrical connection, 1 basic nema 4x enclosure, 2 purged unit – Metrohm NIRS XDS Process Analyzer – SingleFiber User Manual
Page 43: Electrical connection, Basic nema 4x enclosure, Purged unit, 7electrical connection
▪▪▪▪▪▪▪
41
7
Electrical Connection
The XDS Process Analytics Instrument is shipped with an AC line cord, which is used for initial
checkout testing only. When installed in a permanent location, the instrument is to be connected
with a dedicated conduit drop, following all applicable electrical codes. AC Mains wiring is as follows:
Power Requirements:
•
100/240 VAC Selectable
•
50/60 Hz
•
2A / 1.5A
With Air Conditioning (optional) 5A / 2.7A
7.1
Basic NEMA 4X Enclosure
AC Power (Mains) connection is done at the terminal strip inside the XDS Process Analytics enclosure,
as shown in the photo below:
Terminal 1
Terminal 2
Terminal 3
HOT
Neutral
Ground
Intl: Brown
US: Black
Intl: Blue
US: White
Intl: Green/Yellow
US: Green
Do not use terminals 4 to 10. These are pre-wired at the
factory.
Wiring must follow all applicable electrical codes for the area of installation.
7.2
Purged Unit
AC Power (Mains) connection to the purged unit is performed directly in the Electronic Power Control
Unit (EPCU) on the Purge Control Assembly. The terminal block in the main XDS Enclosure is pre-
wired, and must be changed to meet safety requirements. Follow the instructions given in the BEBCO
manual (shipped with the instrument) starting at the bottom of page 12. Follow the wiring diagram
on page 13. A brief overview is given on how to access AC wiring area: