6 axle installation, Axle installation – JLG G5-18A Service Manual User Manual
Page 65

5-5
G5-18A, 2505H, 25.5
Axles, Drive Shafts, Wheels and Tires
5.4.6
Axle Installation
1. Before proceeding, ensure that the machine will
remain in place during axle installation. Block the
front and rear of both tires on the axle that is already
installed on the machine.
2. If applicable, raise the machine using a suitable jack
or hoist. Place suitable supports beneath the frame
and lower the machine onto the supports, allowing
enough room for axle installation. Ensure that the
machine will remain in place during axle installation.
3. Using a suitable jack, hoist or overhead crane and
sling, remove the axle from its support or holding
stand. Balance the axle and prevent it from tipping,
turning or falling while positioning it beneath the
machine. DO NOT raise or otherwise disturb the
machine while installing the axle. Keep the axle
supported and balanced on the jack, hoist or
overhead crane and sling throughout the installation
procedure.
4. Position the axle under the frame, and align with the
holes in the frame.
5. Install the axle with capscrews, locknuts and the axle
plates. Torque the front and rear axles to 420 lb-ft
(569 Nm).
6. Install the drive shaft assemblies. (Refer to Section
5.5.5, “Drive Shaft Installation.”)
7. If reinstalling an axle previously removed from the
machine, position the driveshaft yoke on the axle
according to the alignment marks made earlier. If
installing a new axle, note the position of the
driveshaft yoke at the transmission. Align the
driveshaft yoke on the axle in the same plane as the
yoke on the transmission.
8. Tighten the axle oil drain plug (4), loosen and
remove the axle oil fill plug (5). Tighten the drop box
oil drain plug (4), loosen and remove the drop box oil
fill plug (5). Fill axle with the appropriate oil. Refer to
Section 2.4, “Fluids, Lubricants and Capacities,” for
proper oil and capacities.Rotate wheel hubs 90
degrees so the drain plug (4) becomes the fill plug.
Fill wheel hubs with the appropriate oil. Refer to
Section 2.4, “Fluids, Lubricants and Capacities,” for
proper oil and capacities.
9. Install the wheel and tire assemblies. (Refer to
Section 5.6.2, “Installing Wheel and Tire Assembly
onto Machine.”)
10. Carefully remove the jack, hoist or overhead crane
and sling supporting the axle.
11. Carefully raise machine using a suitable jack or
hoist. Remove supports from beneath frame and
lower machine to ground.
12. Remove blocks from front and rear of both tires on
other axle.
13. Uncap and reconnect steering and brake lines at
their axle fittings. Refer to Section 8.11.2, “Service
Brake Valve,” for brake bleeding procedures.
14. Check hydraulic reservoir oil level.
15. Properly connect battery.
16. Close and secure the engine covers.
17. Start engine. Turn steering wheel several times lock
to lock and check function of brakes. Check for
hydraulic leaks, and tighten or repair as necessary.
18. Remove a Do Not Operate Tag on both ignition key
switch and steering wheel.