3-34 RAID Array 3000 Controller Shelf Hardware User’s Guide

Compaq Confidential – Need to Know Required

Writer: Bob Young Project: RAID Array 3000 Controller Shelf Hardware User’s Guide Comments:

Part Number: EK-SMCPQ-UG. D01 File Name: d-ch3 Installation and Maintenance.doc Last Saved On: 12/4/00 1:08 PM

1.

Power down the controller shelf first (via SWCC) and then power down
the UPS.

2.

Grasp the latches on the front of the controller and pull them forward
until the controller disengages from the shelf (see Figure 3-17).

3.

Remove the controller from the shelf and place it on a flat working
surface.

4.

Remove the two installed cache memory SIMM modules by releasing
the locking clips at each end of the module until it disengages and snaps
into an upright position as shown in Figures 3-19 and 3-20.

SHR-1048

Cache Memory

Modules

Figure 3-19. Controller cache modules

Figure 3-20. Release locking clips