START

STAGE 1

TRIAL FOR

IGNITION

STAGE 2

MAIN BURNER

OPERATION

END

THERMOSTAT (CONTROLLER) CALLS FOR HEAT

SPARK GENERATOR POWERED

First valve (pilot) operator opens

PILOT BURNER OPERATION

Pilot burner lights.

Pilot burner does not light

Module senses

Module

Response

flame current.

S-8600M

After 15 sec. ignition

shut-down. 5 minute

time delay before re-try.

S-8600H

After 15 sec. ignition

system locks out

must be manually reset.

FLAME CURRENT SENSED

• Spark generator off.

• Second valve operator (main) opens.

MAIN BURNER OPERATION

Module monitors pilot flame current.

THERMOSTAT (CONTROLLER) SATISFIED

Valves close, pilot and main burners are off.

POWER INTERRUPTION

System shuts off, restarts

when power is restored.

PILOT FLAME FAILURE

Main valve closes.

Module starts trial for