20
Installationandcommissioning
- Always mount the device upstream a possible injection point in the pipe of a high-conductivity fluid (for
example: acid, base, saline,...).
Correct
flow direction
Incorrect
Correct
Incorrect
Fig. 10:
Air bubbles within the pipe
→
If necessary, use a flow conditioner to improve measurement precision.
7.2.2.
Installation into the pipe of a 8045 with a G2'' nut
In order to ensure a high accuracy of the measurements and good stability of the „flow zero“ point, install
the device into the processed medium at least 24 H before calibration.
1
2
3
5
4
6
FLOW
flow direction
Electrodes
→
Install the S020 fitting into the pipe taking into
account the recommendations in chap. “7.2.1”.
→
Check that there is a seal on the fitting and that it is
not damaged. Replace the seal if necessary.
→
Check that there is a seal (see mark 6, Fig. 11) on
the flow sensor.
→
Insert the nut (see mark 3, Fig. 11) on the fitting.
→
Insert the snap ring (mark 2, Fig. 11) into the
groove (mark 5, Fig. 11).
→
Position the device in order the arrow on the side of
the housing indicates the direction of the flow. the
totalizers will increment.
→
Insert the device (mark 1, Fig. 11) into the fitting.
→
Tighten the nut (mark 3, Fig. 11) by hand on the
device.
Fig. 11:
Installation into the pipe of a 8045 with a G2'' nut
7.2.3.
Installation into the pipe of a 8045 with a clamp connection
Observe the installation recommendations described at chap. 7.2. and in the operating instructions of the
S020 fitting.
In order to ensure a high accuracy of the measurements and good stability of the „flow zero“ point, install
the device into the processed medium at least 24 H before calibration.
English