beautypg.com

3 installation, 1 general installation instructions – YSI P 700 IQ Analyzer User Manual

Page 23

background image

ba76133e01

09/2013

23

P 700 IQ

3.3 Installation

3.3.1 General installation instructions

Pay attention to the following points during installation:

• Installation in the open should be done while the weather is frost-

free.

• Due to its weight, the analyzer always has to be carried by two

people (housing door upward, both people grasp the housing at the
upper C rail and at the housing bottom on the side of the door).

• The analyzer may only be fastened on a wall or fixture with the aid

of the two rails (enclosure upright).

Main steps

Installation of the P 700 IQ includes the following main steps:

1

Installing the housing.
See section 3.3.2,  24.

2

Installing the FM filter membrane module and the
M 1.5 attachment for filtration
.
See section 3.3.3,  35.

3

Inserting the connections into the housing.
See section 3.3.4,  36.

4

Connecting the IQ S

ENSOR

N

ET

cable.

See section 3.3.5.1,  39.

5

Connecting the power line and heat tracing lines.
See section 3.3.5.2,  40.

6

Connecting the liquid containers.
See section 3.3.5.3,  42.

This section describes the installation of the P 700 IQ with
various especially designed accessories. We assume that
the operator uses these accessories. In this section, the
individual scopes of delivery are not distinguished so the
comprehensibility of the instructions is not affected.