Gas sampling and gas conditioning technology

2-1.1.6.1-ME

13.2

VERSION WITH EXTERNAL TEMPERATURE CONTROL

Remove the lid of the connection box. The electrical connection layout is located in the lid.

Insert the mains cable coming from the external temperature controller (min. 3 x 1.5 mm²)

through the threaded cable gland and connect to the appropriate terminals.

Insert the temperature sensor cable through the threaded cable gland and connect to the ap-

propriate terminals.

Screw lid back on.

Figure 6 Electrical connexions at the electronic controller 70304G



14

STARTING

Before starting up check whether the mains power supply voltage corresponds with the infor-

mation stated on the probe's nameplate.

Check the rated value setting on the built-in thermostat or on the external controller.

Switch on mains power supply. The total heating-up time is approximately 2 hours. After about

1 hour the probe is already sufficiently heated for the temperature to have exceeded the tem-
perature failure alarm value (30°C below rated value), but it still takes about another hour until
operating temperature is reached.

The sample gas can now be extracted via the probe after this minimum heating-up time of 2

hours.