Starting, Closing down – M&C TechGroup SP2600-H_C_I_BB_F_0,1GF190 Operator's manual User Manual
Page 17
17
Gas sampling and gas conditioning technology
2-1.1.5.1-ME
14
STARTING
Before starting the equipment for the first time, the safety instructions related to the installation and the
process have to be heeded.
Please consider the appropriate safety requirements and respective measures regarding the mediums
to be extracted.
W A R N I N G !
Please ensure before starting that the mains supply corresponds to
the indication on the type plate !
Be careful when you get in contact with the probe’s surface during
operation. The high surface temperatures may cause burnings.
Protective gloves are to be born and any unauthorized access to
the probe must be made impossible !
We recommend the following procedure:
Check the temperature set value on the integrated thermostat or on the external controller.
N O T E !
In case the adjustment of the temperature set value on the capillary
controller should be changed during operation by more than 30°C
in one step, the thermostat’s excess temperature cut-off is
activated (push the reset key to switch it on again).
Switch on power.
N O T E !
The total heat up time is approximately 40 minutes. The probe is
ready for work after having exceeded the below alarm level value (
30°C below set value ).
W A R N I N G !
In case of insufficient temperature (failure of the probe heating), the
feeding of sample gas must be interrupted by appropriate
measures !
15
CLOSING DOWN
Before closing down, i.e. switching off the heating, the probe should be purged with inert gas or air in
order to avoid condensation of aggressive components from the sample gas.