Operation

69

6.5

System Startup

6.5.1 Initial System Startup Procedure

Initial System Startup is defined as the first or initial startup following installation of the system.

Several additional steps are required prior to the normal startup procedure including the following

Inspection before Initial System Startup, (Section 5.5.2), and Control Parameters Setup (Section

5.5.3.). These steps are required to ensure safe and proper startup of flywheel system and for war-

ranty purposes.

6.5.2 Inspection before Initial System Startup

A Liebert technician will perform the following tasks:

• Visual Inspection

Inspect equipment for signs of damage
Verify installation per drawings
Inspect cabinet for foreign objects
Verify ground conductors are properly sized and connected
Verify all printed circuit boards are configured properly

• Mechanical Inspection

Check all control wiring connections for tightness
Check all power wiring connections for tightness
Check that cabinet is attached to the floor
Check all terminal screws, nuts and/or spade lugs for tightness
Check all cooling pump connections

• Electrical Inspection

Check fuses for continuity
Check and verify UPS DC bus voltage

• Pre-Startup

Perform MLM Pre-Start procedure using Boot Up process with UPS DC bus
Perform MLM Inspection and test
Verify UPS settings and adjustments
Run pumps and fans for several minutes

!

CAUTION

The Initial System Startup shall ONLY be performed under the supervision of a

Liebert-certified service technician in order to ensure proper system operation. Failure to

abide by instructions provided herein may void your warranty.