beautypg.com

3 connecting the interfaces, 4 sealing the connection area – KACO blueplanet gridsave eco 5.0 TR1 User Manual

Page 26

background image

Installation

Page 26

Operating instructions for blueplanet-gridsave eco_EN

Authorised electrician

7.3

Connecting the interfaces

7.3.1 Communication

The monitoring and control of the bidirectional battery inverter and its communication with a compatible KACO

inverter is carried out via the serial communication ports. Each port may have different electrical interfaces availa-

ble, depending on the application.
Only one serial port can be used for each port, however.

Interface

Port 1

Port 2

Application

external

USB type B

Direct PC connection

RS-232/DB9M

Serial connection port

internal

RS-232/RJ-45

RS-232/RJ-45

permanently wired connections (modem or serial

Ethernet adapter for communication via LAN or

Internet)

RS-485/RJ-45

Communication link to connected

KACO inverters

Baud rate

57 600

9600 / with RS-485,

DTR/DCD must be acti-

vated.

NOTE

If port 2 is used as the RS-485 interface and the bidirectional battery inverter is positioned at the end

of this bus line, the switch for the terminating resistors must be set to "ON".

7.3.2 Multi-phase configuration

For configuration of a three-phase system, both RJ-45 interfaces (Sync 1, Sync 2) are activated.

Both connection points are the same and can each be connected to one bidirectional battery inverter in a mul-

ti-phase system.

7.4

Sealing the connection area

1. Check the cabling.
2. Check that the cable fitting is secure and tighten if necessary.
3. Fit the cover and slide back until it engages into position.
4. Check that the position is correct.
5. Screw the fastening screw onto the front of the cover.

NOTE

Any cut-outs in the rear and bottom through-board must be covered following connection. Other-

wise the IP protection rating is reduced and the thermal design will be impaired.