2 moving the sunny central with a crane, 3 installing the roof of the sunny central – SMA SC 500HE-US Installation User Manual
Page 32
![background image](https://www.manualsdir.com/files/818989/content/doc032.png)
5 Transport and Installation
SMA America, LLC
32
SC500HEUS-IA-US_en-14
Installation Manual
5.4.2 Moving the Sunny Central with a Crane
1. For transporting the Sunny Central with a crane use
suitable hoisting steel-wire ropes, hoisting hooks
and loops.
2. Anchor the loops at the intended openings in the
guide rails.
3. Take the heavy weight of the Sunny Central into
account.
5.4.3 Installing the Roof of the Sunny Central
After moving the Sunny Central by crane you must install the roof of the Sunny Central.
1. Apply the roof to the top of the Sunny Central. Keep the front edge of the roof up.
Fasten the PE cable to the fixing point on top of the
Sunny Central.
2. Move the roof forward to apply it to the guid rail.
Move the front edge of the roof down.