3 drilling holes into the base, 3 transporting the sunny central, 1 center of gravity of the sunny central – SMA SC 500HE-US Installation User Manual
Page 28

5 Transport and Installation
SMA America, LLC
28
SC500HEUS-IA-US_en-14
Installation Manual
5.2.3 Drilling Holes into the Base
1. Measure the distances for the holes.
2. Mark the positions of the holes.
3. Drill the holes into the base on marked positions.
4. Put dowels into the drill holes.
5.3 Transporting the Sunny Central
Remove the kick plates before transporting the Sunny Central (see section 5.5.1).
5.3.1 Center of Gravity of the Sunny Central
The center of gravity of the Sunny Central is marked on
the packaging with the symbol on the right.
The center of gravity is not in the middle of the
Sunny Central.
Position of Center of Gravity measured from left front
corner of inverter:
%"/(&3
Drilling into live wires.
Death resulting from electric shock.
• Check the installation location for electric cables laid in the base.
8"3/*/(
Sunny Central may tip over if improperly transported.
Bruises and fractures.
• Pay attention to the center of gravity of the Sunny Central (see section 5.3.1).
• Transport the Sunny Central only as described in this manual.
• Any equipment used for the transport of the Sunny Central must be suitable for the weight of
the Sunny Central.
• Do not tilt the Sunny Central during transport.
horizontal:
47.65 in
vertical:
23.62 in
depth:
18.50 in