5  Transport and Installation

SMA America, LLC

28

SC500HEUS-IA-US_en-14

Installation Manual

5.2.3 Drilling Holes into the Base

1. Measure the distances for the holes.
2. Mark the positions of the holes.
3. Drill the holes into the base on marked positions.
4. Put dowels into the drill holes.

5.3 Transporting the Sunny Central

Remove the kick plates before transporting the Sunny Central (see section 5.5.1).

5.3.1 Center of Gravity of the Sunny Central

The center of gravity of the Sunny Central is marked on
the packaging with the symbol on the right.
The center of gravity is not in the middle of the
Sunny Central.
Position of Center of Gravity measured from left front
corner of inverter:

%"/(&3

Drilling into live wires.
Death resulting from electric shock.

• Check the installation location for electric cables laid in the base.

8"3/*/(

Sunny Central may tip over if improperly transported.
Bruises and fractures.

• Pay attention to the center of gravity of the Sunny Central (see section 5.3.1).
• Transport the Sunny Central only as described in this manual.
• Any equipment used for the transport of the Sunny Central must be suitable for the weight of

the Sunny Central.

• Do not tilt the Sunny Central during transport.

horizontal:

47.65 in

vertical:

23.62 in

depth:

18.50 in