Troubleshooting

SMA Solar Technology AG

80

SB25-30TLST-21-IA-en-13

Installation Manual

6. Insert an insertion tool into the openings of the

terminal contacts.

7. Insert new varistors into the slots (as shown in the

diagram on the right).
Make sure that the labelling points to the left, i.e.
towards the insertion tool.

Result

Measure

☑ There is a conductive connection. The varistor is functional. There must be a different error

in the inverter.

• Contact the SMA Service Line (see Section 15

"Contact" (page 92)).

☑ There is no conductive

connection.

The respective varistor is defective and must be replaced.
Varistor failure is generally due to influences that affect
all varistors in a similar manner (temperature, age,
induced overvoltage). SMA Solar Technology AG
recommends replacing all varistors.
The varistors are specially manufactured for use in the
inverter and are not commercially available. You must
order replacement varistors directly from
SMA Solar Technology AG (see Section 14 "Accessories"
(page 91)).
Only use original varistors that are sold by
SMA Solar Technology AG.

• For replacing the varistors, proceed to step 6.