SMA SB 2500TL-21 Installation User Manual
Page 58

Opening and Closing
SMA Solar Technology AG
58
SB25-30TLST-21-IA-en-13
Installation Manual
7. Release and disconnect all DC connectors.
To do this, insert a flat-blade screwdriver
(blade width: 3.5 mm) into one of the side slots and
pull the DC connectors straight out.
Do NOT PULL ON THE CABLE.
8. Wait until the LEDs, display and fault indicator have gone out.
9. Verify the absence of voltage between L to N at the
AC terminal using a suitable multimeter. The
maximum diameter of the test probe is 2 mm.
☑ If voltage is present, check the installation.
10. Verify that no voltage is present between L and PE
at the AC terminal using a suitable multimeter.
☑ If voltage is present, check the installation.
This manual is related to the following products: