11 Periodic Actions

11.1 Cable Entry

11.1.1 Inserting the Cable into the Cable Feed-Through Plate

Figure 15: Overview of the membranes for inserting the cable

Procedure:

1. Pierce a hole in the respective membrane.
2. Insert the cables in the holes.
3. Cut the cables to length.
4. Attach the cables to an external cable support rail.

/05*$&

Damage to the Power Plant Controller due to moisture penetration
Excessively large or redundant holes in the membranes of the cable feed-through plate can cause moisture to penetrate

the Power Plant Controller.

• Select membranes that match the cable diameter.
• Avoid piercing needlessly large holes in the membranes of the cable feed-through plate.
• Only pierce as many holes in the membranes of the cable feed-through plate as you need for the cables.

Position

Explanation

A

Membranes for cable cross-section from 4.8 mm to 9.7 mm

B

Membranes for cable cross-section from 4.8 mm to 12.0 mm

C

Membranes for cable cross-section from 3.2 mm to 6.5 mm