Measured values submitted to the Power Plant Controller as analog signals will be converted to digital values in the

Power Plant Controller. The measured values in technical units must be calculated from the digital signals. The signals

submitted by the transducer to the Power Plant Controller must be scaled (see Section 13.3, page 57). Scaling of the

measured data is only possible if under PPC > Settings > Modbus server or under PPC > Grid system services >

Device table Power Analyzers > Power Analyzer 1 the entry Yes has been selected in the drop-down list

Customized scaling, or if analog signals are used.