Verifying the installation, Installing the switch on a workbench, Installation preparation – H3C Technologies H3C S12500 Series Switches User Manual
Page 32

22
NOTE:
If the screw holes on the mounting brackets cannot align with the cage nuts on the rack, verify that the
bottom edge of the slide rail aligns with the middle of the narrowest metal area between mounting holes
and that the cage nuts are installed in the correct holes.
Verifying the installation
After the installation is completed, check the installation against the following checklist. Make sure all
check results are positive.
Table 7 Installation checklist
Item
Result
Remarks
Yes
No
The mounting brackets are firmly attached to the switch.
The switch is sturdy and installed in the right position.
The mounting brackets on the switch are firmly attached to the rack.
Installing the switch on a workbench
You can install the switch on a clean, sturdy workbench or on the floor if no rack is available for switch
installation at the site.
Installation preparation
Before placing the switch on a workbench or on the floor, confirm the following preparations:
•
The workbench or floor is sturdy enough to support the weight of the chassis and its accessories.
•
The workbench or floor is correctly grounded.
•
The wall anchors are installed.
a.
Position the installation holes and drill holes.
Make sure each hole is exact in diameter and depth for the anchor.
b.
Assemble each wall anchor by inserting the spade-shaped wedges on the plug into the
grooves on the shank.
c.
Put the assembled wall anchors into installation holes and hammer them into the ground.