Stacking:

Models CME256, CME506, CME656 and CME806

may be stacked together in any combination. Use

kit number KSCME6-30.
1. Remove the front, left side and top panels

from the bottom machine. Discard the top

panel.
2. Remove the front and left side panels

from the top machine.
3. Place the upper machine onto the lower

machine. Check that the tabs on the top of

the freezing compartment in the lower

machine engage the slot in the base of the

upper machine (around the cube port).
4. Fasten the upper cabinet to the lower

cabinet with the hardware (two metal straps

and four bolts) provided with the machine.
5. Knock out 1 hole in the upper left (viewed

from the front) corner of the lower unit’s

back panel. Knock out the hole in the lower

left (viewed from the front) corner of the

upper unit’s back panel.
6. Position the strain reliefs over the

wrapped portion of the stacking kit wire

harness.
Route the Stacking Kit Wire Harness from

the back to the top and bottom machines

thru the holes made in step 5. The harness

is marked which end goes to which

machine. Push the strain reliefs into place

from the back of the machines.
Follow local electrical codes for 24 volt wire.
In the lower unit, route the wire behind the

suction line and thru the snap bushing just

below the AutoIQ Controller. Tape any

excess wire to the insulated suction line.
In the upper unit, route the harness thru the

snap bushing just below the Controller.
Plug one end into each Controller connection

number 7.
7. Place insulation pad from the kit over the

reservoir drain tubing in the upper machine. Make

certain that the insulation is in contact with the

tubing.
8. Return all panels to their normal places.

CME506R, 656R, 806R: AutoIQ Cubers

January 2000

Page 5

Stacking Two Ice Machines Together

Mounting

Strap

Strain

Relief

Stacking Kit Wire

Harness

Mounting

Strap