Appendix A Parameters for Monitoring and Logging
200
EM920 Power Quality and Revenue Meter
6
The value is calculated using a simplified technique as a
relation of the maximum deviation of phase values from a 3-
phase average value to a 3-phase average.
7
The value is calculated using a simplified technique as a
one third of the RMS value of a 3-phase vector sum.
8
Not affected by loss compensation – always indicate
readings at the metering point.
NOTE
Designations of some enginering demands and billing energy
and demand registers are shown using a new short name
notation available in PAS V1.4. By default, PAS uses long
names compatible with older versions of PAS. You can select
a desired notation from the Tools/Options/Preferences tab.
PAS does not allow to store data in files using different data
names. If you have a file uploaded with a previous version of
PAS using long data names, either continue using long data
names, or store data in a new file.
See table below for a list of parameters with short and long
names.
Short Data
Name
Long Data Name
Description
kW IMP ACD
kW IMP ACC DMD
Accumulated demand
kW IMP PRD
kW IMP PRD DMD
Predicted sliding window demand
PF IMP@kVA MD PF IMP@kVA MXDMD
PF (import) at maximum kVA demand
REG1 ACD
SUM REG1 ACC DMD
Billing summary (total) register accumulated demand
REG1 BD
SUM REG1 BLK DMD
Billing summary (total) register block demand
REG1 SD
SUM REG1 SW DMD
Billing summary (total) register sliding demand
REG1
SUM REG1
Billing summary (total) energy register
REG1 MD
SUM REG1 DMD MAX
Billing summary (total) register maximum demand
REG1 TRF1
TOU REG1 TRF1
Billing tariff energy register
REG1 TRF1 MD
DMD1 TRF1 MAX
Billing tariff register maximum demand
TRF1
SEASON TRF1
Generic billing tariff energy register
TRF1 MD
SEASON TRF1
Generic billing tariff register maximum demand