5.3.2 PFC Protection Setpoints

Protection against Voltage Interruptions

The fast disconnection of the capacitor banks is required in the event of short-
term voltage interruptions that would cause damage to the still-charged
capacitors when the voltage is restored.

The No-Volt alarm override condition (see Table 4.6) along with the Hard Switch-
Off action can de-energize the output relays in approximately 25 ms whenever
voltage interruption is detected.

From the Event/Alarm Setpoints Menu, set the setpoint parameters as follows:

Trigger

=

no-U

Operate Limit = none
Release Limit = none
Operate Delay = 0
Release Delay = 3.0 sec
Action

= Hrd.OF

The setpoint release delay defines the amount of time before the PFC returns to
normal operation after the alarm. Set it to a non-zero value (3.0 sec in the above
example).

Over-voltage Protection

Over-voltage override condition prevents damage to capacitors at high voltage
increases that would be caused by faulty connections of the capacitors or by
voltage resonance at a higher frequency.

The high voltage override condition along with the Soft Switch-Off action is
recommended for over-voltage protection. The setpoint can respond to high
measured voltage over 120% of the operating voltage with response time of 0.3
to 300 sec. The setpoint is released without a delay when the voltage returns to a
level of 105-110% of the operating voltage. To avoid non-necessary
disconnecting of the banks, the setpoint is released immediately when the alarm
condition disappears.

From the Event/Alarm Setpoints Menu, set the setpoint parameters as follows (example):

Trigger

=

r.hi. U

Operate Limit = 115-120% of the operating voltage
Release Limit = 110% of the operating voltage
Operate Delay = 10 sec
Release Delay = 0
Action

= SFt.OF

After the alarm, the PFC will not return to automatic operation for a period of time that is

50 times the power factor setpoint operate delay.