MAGNA-LOC
INSTALLATION OF PANEL (
cont
.)
Note: The following steps are for terminating a panel run when the pan width exceeds the width of
the building.
TERMINATION OF PANEL
Last Full Panel
A
A
INSTALLING
PANEL CLIP
STEP
7
"C" Clamp
Floating Rake Zee
Termination Panel
Last Full Panel
2"
Field bend
simulated Male Leg
90°
2"
A
Steps:
1. When the roof panel installation has reached the opposite end of the roof, the last panel run may need to be field modified
to attach to the Floating Rake Zee previously installed.
2. Measure the distance between the vertical leg of the last full panel run and the vertical leg of the Floating Rake Zee
at the eave, endlap, and peak. See dimension “A”.
3. Determine if a full panel will fit between the last full run and the Floating Rake Zee. In most cases it will not fit. If the
full panel will fit, then continue with the installation of the roof. When the last panel is installed the vertical leg of the
male side must fit flush with the Floating Rake Zee.
4. If a full panel is too wide to fit between the last full panel run and the Floating Rake Zee, a panel will have to be field
cut and bent to simulate a male leg.
5. Use the dimension “A” and mark a line on the last panel to serve as the bend line. Mark a second line 2" past the bend line
to be the line you will cut off the excess panel.
6. Field bend the roof panel up 90 degrees to form a vertical leg.
7. Place termination panel between last full panel and vertical leg of Floating Rake Zee making sure the panel fits properly.
8. Clamp termination panel to leg of Floating Rake Zee until Rake Detail is to be installed. (See page 60 for details.)