Preparations for a New Installation of HDLM

In this subsection, you will perform such preparations as backing up the

HDLM management-target devices, applying AIX patches, and performing

hardware setup.

When using HDLM in a cluster configuration, make sure to perform the

operations described in the following sub-sections on all hosts that comprise

the cluster.

Perform Operations for HDLM Management-Target Devices

If you have already defined physical volumes and have been running the

HDLM management-target devices, perform the following procedure:

1

.

Terminate the processes of all applications that are accessing the HDLM

management-target devices.

2

.

If necessary, back up all HDLM management-target devices to a medium

such as tape.

3

.

Unmount the disks.
If the HDLM management-target devices are mounted, unmount them as

follows:

¢

First, execute the command below to check the current settings.
# mount -p
The current settings will be output as follows:

Figure 3-2 Execution Result Example of the Mount -p

Command (Preparations for a New Installation of HDLM)

In this example, assume that HDLM manages the shaded portion of

the devices.

¢

Execute the following command to unmount the disk.
# umount /mntpt

4

.

Execute the following command to inactivate the applicable volume

group:
# varyoffvg volume-group-name

Set Up the Hardware

Check the topology (Fabric, AL, etc.) and perform setup as appropriate.

1

.

Set up the storage system.

Creating an HDLM Environment