Notice – GE Industrial Solutions Arc Vault Protection System User Manual
Page 25

DEH-41483 Rev. 3
Arc Vault™ Protection System
Equipment
Installation
© 2011 General Electric All Rights Reserved
17
Figure 4-3 Floor plan and cable entry space
ASSEMBLY AND INSTALLATION OF SWITCHGEAR
EQUIPMENT
General Requirements
Before assembling or installing the switchgear equipment,
all components should be available at the site location. This
will facilitate switchgear component identification as well
as installation. The foundation should be prepared in
accordance with the instructions in SECTION 4 Equipment
Installation, and all embedded conduits installed and
capped.
NOTICE
If rollers are to be used for movement of the
equipment to its permanent installation, it is
recommended that the shipping skid not be removed
until the equipment is placed in position over the
anchor bolts.
If a transformer is not part of the installation, and/or the
equipment has been split for shipment, place the center
section on the foundation first. Assemble the remaining
sections outward from the center section, in each direction.
If the switchgear equipment is part of a Load Center Unit
Substation, the transformer section should be set on its pad
first in accordance with the instructions furnished with the
transformer. All remaining sections of the switchgear
should then be installed.
NOTICE
Before assembling and installing the switchgear
equipment, the foundation must be absolutely level
and clear of debris to prevent damage and possible
mis-operation of the switchgear equipment.
Detailed Assembly and Installation Instructions (indoor)
The recommended procedure for installation of an indoor
switchgear or Load Center Unit Substation is as follows:
1. POSITION THE EQUIPMENT-Position the equipment or
sections of the complete equipment in their final location.