Gas sampling and gas conditioning technology
10-1.1.1-ME
13
INITIAL OPERATION
Prior to initial operation, the system and process-specific safety measures must be observed !
The following steps must be carried out prior to initial operation:
Prior to initial operation, compare the system voltage with the voltage shown on the rating plate;
Connect the air conditioning unit to the mains;
Connect status contact ouput, if necessary ;
Operate the
“Power/On” switch (green LED lights).
Check the nominal temperature of 500°C at the temperature controller (see Figure 2).
When operational readiness has been reached (about 15 minutes), the 1 lights upin the display.
W A R N I N G !
The air conditioning unit is operated with min. 73 psi and max.
145 psi inlet pressure.
N O T E !
The maximum gas flow is 15Nl/min.
14
SWITCH OFF
N O T E !
The place of installation of the air conditioning unit must be
remain free from frost also during time when the unit is switched
off !
Switch off the device and disconnect the pressure air.
No more particular measures are required for switch off.
15
MAINTENANCE
Before carrying out maintenance work, the system and process-specific safety measures must be
observed!
W A R N I N G !
The air conditioning is operated with max. 145 psi inlet pressure.
High voltage and high pressure. Disconnect the mains plug and
the pressure air inlet before opening the housing!