Installation and assembly

Technical service - Rights reserved MCZ S.p.A. - Reproduction prohibited

3.4.1. Connections to the system

Make the connections to the corresponding fittings shown in the

diagram on the previous page. Make sure the pipes are not placed

under tension or undersized.

IMPORTANT
IT IS STRONGLY RECOMMENDED TO WASH THE

ENTIRE SYSTEM BEFORE CONNECTING IT IN ORDER

TO GET RID OF RESIDUES AND DEPOSITS.
Upstream from the stove, always install shutters so

as to disconnect it from the plumbing system should

it be necessary to move it, or when it requires

routine and/or special maintenance.
Connect the stove using hoses so that the stove is

not too strictly connected to the system, and to allow

slight movements.

The pressure discharge pipe should be tentatively

placed in a pitcher or funnel to keep water from

wetting the floor or the structure in the event of

excessive pressure.

3.4.2. System filling

To fill the system, the stove is equipped with a tap (D), with a non-

return valve, for manual filling of the heating system. During this

operation, any air in the system is released by the automatic vent valve

at the upper left of the boiler body (under the ceramic top).
To ensure the valve vents correctly, it is advisable to loosen the grey

cap one turn and to keep the red cap blocked

(see figure)

The filling pressure of the system WHEN COLD must be

1 bar.
During operation, if the system pressure drops (due to evaporation of

dissolved gases in the water) to values lower than the minimum

indicated above, the user must use the filling valve to bring the

pressure back up to its normal pressure.
For proper operation of the stove WHEN HOT, the pressure in the

boiler must be 1.5 bar.
To monitor the pressure of the system, install down the line

from the bibcock (D) a pressure gauge with a scale of 0-5 bar.

This is to be done by the installer.
Upon completion of this operation, always close the tap.

3.4.3. Water characteristics

The characteristics of the water used to fill the system are very

important to prevent the build-up of mineral salts and the formation of

incrustations along the pipes, in the boiler and in the heat exchangers

(especially plate heat exchangers for the heating of domestic water -

see chapter 4.13)
Therefore, please GET YOUR PLUMBER'S ADVICE

CONCERNING:

Filling tap (D)

C

D

E

Pressure discharge pipe (3 bar)

Grey plug loosened

1 turn

Red plug blocked