8.5.2 Connecting the PV Modules

1. Open the Sunny Central as described in chapter 10 "Opening the Sunny Central" (page 60).

2. Cover the PV modules.
3. Switch off the fuses in the DC distribution boxes (e.g. Sunny Central String-Monitor) and secure

them against reconnection.

4. Follow all safety precautions of the module manufacturer.
5. Lead the cables into the Sunny Central, as described in Section 6 "Attaching the Conduits"

(page 35).

6. Connect ground cables to the terminal blocks at the

bottom right of the Sunny Central (see also Section
8.4 "Requirements for Connecting cables to Rails"
(page 47)).

7. Open the screw terminal completely.
8. Plug the copper inner conductor of the cable into the

screw terminal.

9. Tighten the screw terminal using an Allen key. The

required torque is 42 ft-lbs (57 Nm).

10. Connect all grounding cables of the modules as

described above.

The illustrations in this chapter show a Sunny Central which is equipped for connection to
9 or 18 DC strings.

DANGER

Voltage is present in PV modules exposed to light.
Death resulting from electric shock.