8.5 Connection of the PV Modules

8.5.1 Requirements

Do not connect the PV modules until the optional communication cables have been connected (see
section 7 "Connecting Optional Communication Devices" (page 38)). DC distribution boxes (e.g.
Sunny Central String-Monitor) must be installed between the PV modules and the Sunny Central,
where the PV module cables are gathered and led to the Sunny Central.
The Photovoltaic System Grounding must be installed per the requirements of Sections 690.41
through 690.47 of the National Electrical Code, ANSI/NFPA 70 and is the responsibility of the
installer.

Technical Data for the Connection of the PV Modules

Torques and Cable Sizes for DC+, DC– and PE

Copper conductors only - use solid, or stranded copper only.
The Sunny Central can be delivered with 6, 7, 8 or 9 DC fuses. Every fuse has a separate rail to which
1 or 2 DC strings can be connected. Below you find the cable sizes and torques for the connection
of the strings.

Number of strings

6 (12), 7 (14), 8 (16) or 9 (18)

DC input voltage

330 - 600 V DC

Max. DC current

1600 A

DC fuses

Number of DC

Strings

Cable Size

Torque

max. DC fuse

rating

6

6

800 kcmil

All 194 °F (90 °C) copper

wire, 55 ft-lbs (75 Nm)

tightening torque

450 A

12

350 kcmil

7

7

600 kcmil

All 194 °F (90 °C) copper

wire, 55 ft-lbs (75 Nm)

tightening torque

400 A

14

300 kcmil

8

8

500 kcmil

All 194 °F (90 °C) copper

wire, 55 ft-lbs (75 Nm)

tightening torque

350 A

16

4/0 AWG

9

9

400 kcmil

All 194 °F (90 °C) copper

wire, 55 ft-lbs (75 Nm)

tightening torque

300 A

18

4/0 AWG