beautypg.com

SMA SC 500U Installation User Manual

Page 27

background image

SMA Solar Technology AG

Installation Guide

SC500U-IUS093411

27

1. Remove kick plates on the front and on the rear of both cabinets of the Sunny Central using a

torx screwdriver.

2. Remove the kick plates by pulling them toward you

(see figure on the right).

3. Load the cabinets on a forklift or a crane fork from

the front (see section 5.3.1 "Equipment for
Transport" (page 25)).

4. Transport the cabinets to the installation site. During

transport, be sure to follow all the instructions
provided in section 5.3 "Transporting the Sunny
Central" (page 25).

5. Place the Control and Interface Cabinet of the Sunny

Central on the base. The holes in the Sunny Central
and the anchor studs in the base must fit.

6. Install the Magnetics Cabinet with a clearance (A) of

about 20 inches (50 cm).

7. Open the Control Cabinet as described in section 10.1 "Opening the Control Cabinet"

(page 60).

8. Open the Magnetics Cabinet as described in section 10.3 "Opening the Magnetics Cabinet"

(page 62) .

Stop S

tart

A