5.3 Transporting the Sunny Central
Remove the kick plates before transporting the Sunny Central (see section 5.4.1 "Removing the Kick
Plates from the Sunny Central" (page 26)).
5.3.1 Equipment for Transport
The Sunny Central is shipped in two parts. The following equipment can be used for the transport of
the Sunny Central:
• Crane with an according fork (A) for the transport of the Sunny Central.
• Forklift or pallet truck (B).
Example of Transporting the Sunny Central Cabinet
Any equipment used for the transport of the Sunny Central must be suitable for the weight of the Sunny
Central. The left cabinet (Magnetics Cabinet) of the Sunny Central weighs approx. 4,740 lbs.
(2,150 kg) and the right cabinet (Control and Interface Cabinet) weighs approx. 2,425 lbs.
(1,100 kg).
WARNING
Sunny Central may tip over if improperly transported.
Bruises and fractures.
• Pay attention to the center of gravity of the Sunny Central (see section 5.3.2 "Center
of Gravity of the Sunny Central" (page 26)).
• Transport the Sunny Central only as described in this manual.
• Any equipment used for the transport of the Sunny Central must be suitable for the
weight of the Sunny Central.
• Do not tilt the Sunny Central during transport.
Stop S