A.1 Notch vertical adaptors at captured mullions according to FIGURE 19. Horizontal adaptors are straight

cut. Install vertical adaptors first, leaving an equal overlap into each pocket. Refer to VERTICAL
SPLICING, page 13 & 14 if vertical mullion is spliced within a spandrel lite. Transition adaptors must be

installed after mullion splice is sealed.

A.2 For SSG mullions, install locator leg into one of the glazing reglets. Secure to mullion with #10 x 2 1/2˜ (1

3/4" glazing) and #10 x 3" (2" glazing) Phillips Flat Head screw 3˜ from the ends and 12˜ O.C. SEE

FIGURE 20.

A.3 Install horizontal adaptors maintaining an equal gap at each end. Once all adaptors have been installed

in the opening, seal all joints between the vertical and horizontal adaptors as well as screw heads. SEE
FIGURE 21.

13/32"

13/16"

Cut length

Seal head of screw
after installing

If pilot hole is needed,
seal hole in mullion
prior to attaching adaptor

Zone plug must be

installed & sealedprior to

installing glazing adaptors

Seal adaptor to mullion;
marry all joints

Seal joint

at adaptors

Seal

screw head

FIGURE 19

Notch at Vertical Adaptors

(adaptor for 1/4" infill shown; 1" similar)

FIGURE 20

Installing Glazing Adaptors

FIGURE 21

Sealing Glazing Adaptors