The schedule function can be programmed for inactive,

single set point, or dual set point operation.

When schedule is configured for inactive, chilled water

pump relay remains energized continuously but is not used
since chiller is usually controlled by remote chilled water
pump interlock contacts.

When unit is configured for single set point operation,

chilled water pump relay is energized whenever chiller is in
occupied mode regardless of whether chiller is running. When
chiller is in unoccupied mode, chilled water pump relay is
not energized.

When unit is configured for dual set point, chilled water

pump relay is energized continuously, in both occupied and
unoccupied modes. Occupied mode places occupied chilled
water set point into effect; unoccupied mode places unoc-
cupied chilled water set point into effect.

The schedule consists of from one to 8 occupied time pe-

riods, set by the operator. These time periods can be flagged
to be in effect or not in effect on each day of the week. The
day begins at 00

and ends at 24.00. The machine is in

unoccupied mode unless a scheduled time period is in ef-

fect, If an occupied period is to extend past midnight, it
must be programmed in the following manner: occupied pe-

riod must end at

hours (midnight); a new occupied

period must be programmed to begin at

hours.

NOTE: This is true only if the occupied period starts at

(midnight). If the occupied period starts at a time

other than midnight, then the occupied period must end at

hours (midnight) and new occupied period must be

programmed to start at

in order for the chiller to stay

in the occupied mode past midnight.

The time schedule can be overridden to keep unit in oc-

cupied mode for one, 2, 3 or 4 hours on a one-time basis.
See Example 9.

All subfunctions of schedule function are password pro-

tected except the override subfunction,

.

word entry into subfunctions

through

is done through service function. See page 44, logging on/
logging off.

Figure 9 shows a schedule for an office building with the

chiller operating on a single set point schedule. The sched-
ule is based on building occupancy with a 3-hour off-peak
cool-down period from midnight to 3 a.m. following the
weekend shutdown. To learn how this sample schedule would
be programmed, see Example 9.
NOTE: This schedule was designed to illustrate the pro-

gramming of the schedule function and is not intended as a
recommended schedule for chiller operation.

Example 9

Using

the

Schedule Function

DISPLAY

O V R D 0

O V R D 3

O V R O 0

C L O C K 0

C L O C K 1

C L O C K 6 5

PERIOD 1

00.00

M O N N O

M O N Y E S

TUE YES

T U E N O

P E R I O D 2

occ 00 00

occ 7 00

00.00

18 00

M O N N O

MON YES

T U E N O

TUE YES

W E D Y E S

W E D N O

No schedule override
in effect

3 hours override in effect

Override cancelled

Schedule function is inactive

Schedule function is enabled
through local unit clock

Schedule function is enabled
throuah CCN clock 65

Define schedule period 1

Start of occupied time

For this example, first
period should stat-t here

so no entry

Start of unoccupied time
(end of period) For this

period 1 should

end at 3:00 a m.

Period 1 ends at 3:00 a m

Monday is now flagged no
for

1 To out

into’ effect on
Monday must be flagged

Monday is now fla
period to be in e

ged for

ect

For this example, period
is to be in effect on Monday
only All other days must
checked to be sure that thev
are flagged no. If any day
flagged yes, change to no

Tuesday is now flagged
no for period

Define schedule period 2

Start of occupied

will start

Start of unoccupied time
(end of period) For this
example, period 2 should
end at 18:00 (6:00 p m )

Period 2 ends at 18:OO

(6:00 p m )

Monday is now flagged no

for period 2 To put period 2

into effect on Monday,
Monday must be flagged yes

Monday is now flagged for
period 2 to be in effect

Tuesay is now flagged no
for period 2 To put period 2

into effect on Tuesday,

Tuesday must be flagged

Tuesday is now flagged for

period 2 to be in effect

For this example, period 2
is to be in effect only on
Monday and Tuesday
All other days must be
checked to be sure that

they are flagged no. If

a day is flagged yes,
change to no

Wednesday is now flagged
no for period 2

CCN

Carrier Comfort Network

Example 9 continued next page.

4 6