beautypg.com

3 maintenance, 1 regenerating the spm, Maintenance – Metrohm 850 Professional IC MSM-HC MCS Prep 3 User Manual

Page 108

background image

5.10 Sample preparation module (SPM)

■■■■■■■■■■■■■■■■■■■■■■

98

■■■■■■■■

850 Professional IC Anion – MSM-HC – MCS – Prep 3

Caution

In the case of reduced capacity or high backpressure, the SPM must be
regenerated (see Chapter 5.10.3.1, page 98), cleaned (see Chapter
5.10.3.2, page 99)
or replaced (see Chapter 5.10.3.3, page 101).

5.10.3

Maintenance

5.10.3.1

Regenerating the SPM

If the neutralization units are loaded with certain heavy metals (e.g. iron)
or organic impurities, these can no longer be completely removed with
the regeneration solution (100 mmol/L HClO

4

) normally used. The capacity

of the neutralization units is affected by this, which can lead to a reduced
detection sensitivity. If such capacity problems occur at one or more posi-
tions, the neutralization units must be regenerated:

Regenerate the SPM

Regenerate the SPM as follows:

1 Disconnecting the SPM from the system

Switch off the instrument.

Disconnect capillary connections of the SPM from the system.

2 Regenerate the SPM

Caution

The pump tubings made of PVC must not be used for rinsing with
solutions containing organic solvents. In this case, other pump
tubings must be used for rinsing.

Rinse the 3 neutralization units with the following solutions for
about 15 minutes each:

Contamination with heavy metals:

1 mol/L H

2

SO

4

+ 0.1 mol/L oxalic acid

Contamination with organic cationic complexing

agents:
0.1 mol/L H

2

SO

4

/ 0.1 mol/L oxalic acid / acetone 5%

Severe contamination with organic substances:

0.2 mol/L H

2

SO

4

/ acetone

≥ 20%