T-armor, Valley - floating – Metal Sales T-Armor Series User Manual
Page 61
© Metal Sales Manufacturing Corporation / Subject to change without notice 09/14
61
T-ARMOR
VALLEY - FLOATING
INSTALLATION NOTES
Panel Clip w/ (2) #14-13 Deck Screws
Bearing Plate
#14-13 Deck Screws (6" oc)
Valley
Offset Cleat
Tube Sealant (Between Panel Ribs)
Tube Sealant (in panel hem)
Double Bead Tape Sealant
T-Armor Panel
Valley Plate (by others)
3:12 Slope
Minimum
3" min
9" max
All Valley flashings must be installed prior to panel
installation.
1. Install new Valley flashing over top of rigid board
insulation. To hold Valley in place fasten to substrate
with fasteners at 4'-0" oc.
2. If two or more flashings are required, lap the upslope
flashing over the previously installed flashing by a
minimum of 6" placing two rows of Tube Sealant
between the flashings. Locate beads of Tube Sealant so
that it does not press out of the lap. Do not install any
fasteners through the Valley lap.
3. Apply a continuous row of Double Bead Tape Sealant across each side of the Valley flashing.
4. Install Offset Cleats on Double Bead Tape Sealant and secure with #14-13 Deck Screws at 6" oc.
5. Install the panels by hooking the hemmed edge of the panel (see page 76 for Hemming Instructions) around the
end of the Offset Cleats.
6. Apply Tube Sealant up the side and across the top of the panel ribs before installing the next panel.
Metal Decking (By others)
*Panel cap not shown for clarity