T-ARMOR
58
CAUTION
In locations where heavy rainfall or severe ice and
snow may occur, Metal Sales' standard gutters may
not be suitable for use.
All Gutter flashings must be installed prior to panel
installation.
1. Install new Box Gutter flashing over top of rigid board
insulation. To hold Box Gutter in place fasten to
substrate with fasteners at 4'-0" oc.
2. Apply a continuous row of Double Bead Tape Sealant
across the Box Gutter flashing.
3. If two or more flashings are required, lap the flashing
over the previously installed flashing by a minimum of
2" placing two rows of Tube Sealant between the
flashings and secure with Pop Rivets, 2.5" oc.
4. Field-bend and place Gutter Straps at 2'-0" oc
(maximum).
5. Install Offset Cleat at Double Bead Tape Sealant
locations and secure with #14-13 Deck Screws at 1'-0" oc.
6. Install the panels by hooking the hemmed edge of the panel (see page 76 for Hemming Instructions) around the
end of the Offset Cleat.
7. Apply Tube Sealant up the side and across the top of the panel ribs before installing the next panel.
BOX GUTTER - FLOATING
1
/
2
:12 Slope
Minimum
INSTALLATION NOTES
Panel Clip w/ (2) #14-13 Deck Screws
Bearing Plate
T-Armor Panel
Tube Sealant (Between Panel Ribs)
#14-13 Deck Screws (1'-0" oc)
Offset Cleat
Tube Sealant (in panel hem)
Double Bead Tape Sealant
Moisture Barrier (by others)
1
/
8
"x
3
/
16
" Pop Rivet (1 per Strap)
Box Gutter
Gutter Strap (2'-0" oc)
9" max
Metal Decking (By others)
*Panel cap not shown for clarity