Installation instruc tio ns – Poison Spyder YJ CAGE LOWER A-PILLAR KIT User Manual
Page 2

INSTALLATION INSTRUC
TIO
NS
Poison Spyder Customs • YJ CAGE LOWER A-PILLAR KIT INSTALL
Page 2
©2010 POISON SPYDER CUSTOMS, INC. • 951-849-5911 • WWW.POISONSPYDER.COM
adjustment. Leave the bolts only snug
enough to hold the A-Pillars in place but
loose enough to allow them to slide up and
down within the slots.
7. Position the Foot Plates beneath each
A-Pillar. Make sure the plates are positioned
so that the A-Pillar lands as close to the
center as possible, but so the bolt holes
that must be drilled through the floor are
correctly located away from any obstructions
underneath the floor. Tack-weld the A-Pillars
to the Foot Plates.
8. Drill the four bolt holes into the Jeep’s
floorboards, using the holes in each of the
Foot Plates as your drill guide. Bolt the Foot
Plates into place (hardware not included in
Kit).
9. Continue with the rest of your cage
fabrication. Attach the tubular upper A-pillars
of your cage to the top surface of the Poison
Spyder Lower A-Pillar. Only tack weld this
joint during initial fabrication. Wait until the
entire cage is complete, to remove the cage
and fully weld all of the seams that were only
tack-welded during initial assembly.
Congratulations, you have completed the
installation of your Poison Spyder Lower A-Pillar
Kit!