POWER WIRING INSTALLATION NOTES
071608
D
164201603-5
DESCRIPTION:
DATE:
DRAWING NO:
SHEET:
REVISION:
INSTALLATION INFORMATION
EATON Powerware
®
9390 UPS (20–80 kVA) Installation and Operation Manual
S 164201603 Rev 2 www.powerware.com
A-11
Table E. INPUT/OUTPUT Ratings & External Wiring Requirements for the Powerware 9390-40/20
Units
Rating 50/60 Hz
Basic Unit Rating at 0.9 lagging
pF load
kVA
kW
20
18
20
18
20
18
20
18
20
18
Input and Bypass Input
Output
VOLTS
VOLTS
208/220
208/220
380
380
400
400
415
415
480
480
AC Input to UPS Rectifier
(0.98 min. pF)
Full Load Current plus Battery
Recharge Current
(3) Phases, (1) Ground
A
Amps
60
34
33
32
30
Minimum Conductor Size
Number per Phase
AWG or kcmil
(each)
2
(1)
6
(1)
6
(1)
6
(1)
6
(1)
AC Input to UPS Bypass
Full Load Current
(3) Phases, (1) Neutral-if required,
(1) Ground
B
Amps
56/53
31
29
28
24
Minimum Conductor Size
Number per Phase
AWG or kcmil
(each)
2
(1)
6
(1)
6
(1)
6
(1)
6
(1)
DC Input from Battery to UPS
(1) Positive, (1) Negative
C
Vdc
Amps@
(2.0V/cell)
384-480
51
432-480
51
432-480
51
432-480
51
432-480
51
Minimum Conductor Size
Number per Pole
AWG or kcmil
(each)
2
(1)
2
(1)
2
(1)
2
(1)
2
(1)
AC Output to Critical Load
Full Load Current
(3) Phases, (1) Neutral-if required,
(1) Ground
D
Amps
56/53
31
29
28
24
Minimum Conductor Size
Number per Phase
AWG or kcmil
(each)
2
(1)
6
(1)
6
(1)
6
(1)
6
(1)
Neutral Bonding Jumper
Minimum Conductor Size
Number (See Note 7)
-
AWG or kcmil
(each)
4
(1)
6
(1)
6
(1)
6
(1)
6
(1)
NOTE Callout letters
A
,
B
,
C
, and
D
map to Drawing 164201603-4, sheets 1 of 5,
Read and understand the following notes while planning and performing the installation:
1.
Refer to national and local electrical codes for acceptable external wiring practices.
2.
Material and labor for external wiring requirements are to be provided by designated
personnel.
3.
For external wiring, use 90
C copper wire. See the appropriate information in Table E
through Table J. Wire sizes are based on using the specified breakers.
4.
Wire ampacities are chosen from Table 310-16 of the NEC. Wire is 90
C specification.
5.
If installing, as part of the UPS system, a maintenance bypass without a rectifier input
breaker, a minimum of two separate feeds with upstream feeder breakers, or one feed with
two upstream feeder breakers, must be provided: one for the UPS and one for the
maintenance bypass input. DO NOT use one feed or a single‐feeder breaker to supply
both the UPS and the maintenance bypass.