MCZ PowerBox COMPACT User Manual
Page 17

Chapter 3
INSTALLATION AND USE MANUAL
page
17
Installation and fitting
Technical service - Rights reserved MCZ S.p.A. - Reproduction prohibited
It is very important to comply with the measures for
positioning the base of the product. Make sure that
the support anchoring surface and the wall are
perpendicular. Also make sure that that the screws
secure the machine to the support.
It is mandatory to mount the unit to the base, since
during maintenance the combustion chamber must be
extracted, causing the barycentre of the equipment to
shift forward. If the product is not anchored to a
surface, it runs the risk of loosing its stability.
The unit can be installed at the desired level, creating a structure of the
opportune height. This support must be constructed in inflammable
material.
MCZ declines any responsibility for possible damages
to persons or things if the aforementioned warnings
are not respected.
3.4. REMOVAL OF COMPENSATION FRAME
To avoid damage to the border frame (C) located around the fire door,
it is recommended to remove it before mounting the Powerbox to the
base (E) and to put it in a safe place. For removal, see
chap. 3.13
3.5. INSTALLATION OF PELLET LOADING CHUTE
(LINK)
Before positioning the unit, you will need to decide on which side the
chute for fuel loading will be installed.
The Powerbox Link is provided with two straps, the connecting tube
and the chute with a small door.
The chute can be assembled on the right side, the left side or on the
front. The connecting tube is one meter long.
B
B
C
C
D
E
Mounting to the base