Installation and fitting

Technical service - Rights reserved MCZ S.p.A. - Reproduction prohibited

It is very important to comply with the measures for

positioning the base of the product. Make sure that

the support anchoring surface and the wall are

perpendicular. Also make sure that that the screws

secure the machine to the support.

It is mandatory to mount the unit to the base, since

during maintenance the combustion chamber must be

extracted, causing the barycentre of the equipment to

shift forward. If the product is not anchored to a

surface, it runs the risk of loosing its stability.


















The unit can be installed at the desired level, creating a structure of the

opportune height. This support must be constructed in inflammable

material.

MCZ declines any responsibility for possible damages

to persons or things if the aforementioned warnings

are not respected.

3.4. REMOVAL OF COMPENSATION FRAME

To avoid damage to the border frame (C) located around the fire door,

it is recommended to remove it before mounting the Powerbox to the

base (E) and to put it in a safe place. For removal, see

chap. 3.13

3.5. INSTALLATION OF PELLET LOADING CHUTE

(LINK)

Before positioning the unit, you will need to decide on which side the

chute for fuel loading will be installed.
The Powerbox Link is provided with two straps, the connecting tube

and the chute with a small door.
The chute can be assembled on the right side, the left side or on the

front. The connecting tube is one meter long.

B

B

C

C

D

E

Mounting to the base