beautypg.com

7 - start-up and test, Installation completion checklist, 1 the unit must be properly secured to the island – Gasboy 9800Q Series User Manual

Page 75: 5 the unit must be properly grounded, Start-up, 7 – start-up and test, Installation completion checklist -1 start-up -1, Caution

background image

MDE-4340A Series 9800Q Pumps and Dispensers Installation/Operation Manual · January 2006

Page 7-1

Start-Up and Test

7 – Start-Up and Test

Installation Completion Checklist

Review the information below to verify the proper installation of the Series 9800Q dispensing
unit. If the installation does not meet criteria listed, correct the problem before the start-up is
performed.

CAUTION

CAUTION

To avoid damage to the CPU PC board, verify that the RESET COMPLETE, FAST
FLOW, SUBM. STARTER DRIVE, and SLOW and FAST SATELLITE RETURN
wires are not shorted to conduit or chassis.

1

The unit must be properly secured to the island.

2

All plumbing must be complete and tight. All liquid-carrying lines must be checked for leaks.

3

When DC pulser or RS-485 lines are used in the pump for connecting to Gasboy Fuel
Management Systems, the AC and DC wires must not share any conduits, junction boxes, or
troughs, except as noted in

“Wiring” on page 5-1

, Conduit and Pulse Output or RS-485 Wiring

and the TopKAT Installation Manual, Communication Requirements.

4

All conduit work must be complete. All junction box covers must be secured. Conduits should
not be sealed until the wiring is verified through proper operation.

5

The unit must be properly grounded.

CAUTION

CAUTION

Before any testing begins, remove any water in the tank through a fill opening, using a
suitable pump. Do not use the Gasboy pump or remote dispenser and submersible pump
to remove water. Serious damage may occur.

6

A sufficient volume of fuel must be put in the tank to ensure that the liquid level is above the
bottom of the suction pipe (suction pumps) or is high enough to allow the submersible pump to
operate efficiently (remote dispensers).

Start-Up

After successfully verifying the installation against the completion checklist, the unit is ready
for start-up. Follow the procedure below to perform an orderly start-up of the Series 9800Q.

1

Verify if all switches on the CPU PCB are set properly for the various operating conditions as
explained in

“Pump/Remote Dispenser Operation” on page 6-1

.