Page 3-2 MDE-4340A Series 9800Q Pumps and Dispensers Installation/Operation Manual · January 2006
12
DO NOT back-fill the tank or supply line with cinders or ashes. (Back-fill with clean sand,
crushed rock, or pea gravel).
13
DO NOT use black iron pipe or fittings for underground installations. (Use only new
galvanized or fiberglass* pipe and fittings). *Install all fiberglass pipe and fittings according to
manufacturer's specifications and requirements.
14
DO NOT use power line wiring of inadequate capacity. (Use gauge specified by the wiring
diagram or wire chart provided in
).
15
DO NOT use a circuit breaker of improper size (See
16
DO NOT install fill pipe to tank where it can be submerged with standing water.
17
DO NOT use the Gasboy fuel dispensing equipment to remove water ballast from the storage
tank.
18
DO NOT use gaskets on covers of explosion-proof type boxes. The sealing compound found
around wires at all junction box entrances is a requirement of the National Electrical Code and
should not be disturbed. Ensure that the mating surfaces between the junction box and cover
are free of dirt, debris, nicks, and scratches. Tighten junction box covers before replacing
panels.
19
DO NOT use knock-out boxes or flexible conduit for installing this unit. All power and
lighting wires should be run in threaded, rigid, metal conduit. All threaded connections must
be drawn up tight with five (5) threads minimum engagement. Only one opening in the AC
junction box is provided with a plug at the factory. On completion of the installation, it is the
installer's responsibility to ensure that any unused openings are plugged.
Foundation
When constructing the pump island for the dispensing equipment, be sure to extend the island
excavation beyond the depth of the frost line. Leave open an area from the inside edge of the
unit's base as shown on the specific base layout. Unless required by local regulations, do not
cement the pipes and conduits into the island. The open area within the base will provide
access for future servicing of the fittings, check valve and conduit assemblies. Fill in the
boxed-in section with dry sand to keep condensation in the pump housing to a minimum and to
help prevent fogging of the totalizer window.
Secure the pump/remote dispenser to the island using anchor bolts through the two mounting
holes, which are 13 inches (330mm) apart and are indicated on each base layout by an X. If the
dispensing unit is not securely fastened to the island, supply line leaks at unions and pipe joints
may occur. Use one of two types of bolts to anchor the pump to the island. Use two (2) 1/2" x
5" (13mm x 125mm) machine bolts imbedded in the concrete, or, to meet minimum UL and
API requirements for universal interchangeability of pumps, use two 1/2" x 3 1/2" (13mm x