Wiring

Operating Manual PSSu K F FCU
1002391-EN-04

32

On dual-pole outputs, both terminals (O00 +/- or O01 +/-) must be used from an output cur-
rent of 2.18 A per load.

Function test during commissioning

An error must be simulated for each safety-related output during commissioning: The antici-
pated error reaction must occur when an output has a short circuit to a supply voltage.

INFORMATION
The short circuit test must be performed on the load and not on the output
terminal.

6.6